Set Requisition Preferences at the Project Level

Previous TopicNext TopicContents

At the project level, cost options are set on the Project Settings Dialog Box, on the Cost Options tab.

  1. Right-click on a project, and choose Project Settings to open the Project Settings Dialog Box.
  2. Click the Requisitions tab.
  3. Set the Schedule of Values options.
  4. Set the Retainage Calculation options.
  5. Set the Tax Calculation options.
  6. Click Save when finished.

    Note: The Requisitions tab in Project Settings only affects new contracts and purchase orders, not existing ones.

Related Topics

Set Cost Options and Requisition Preferences