After creating a procurement item, you should first add the individual components (scope items) that make up the procurement item up for bid.
New scope items appear in the left column of the Bid Tabulation tab. You can add as many scope items as necessary to the procurement item.
To add scope items to the procurement item:
Note: Click Add Detail Items to the left of the sub item to which you want to add a detail item. See Add Detail Items to Sub Items.
Tips:
Click Re-Sync to recalculate the values in the Total column to make the values at the top level equal the values entered in the sub-levels. Clicking Re-Sync "rolls up" the values from the sub-levels, and recalculates the top level values. This is beneficial in instances where the top-level values were entered before the lower values, and thus may no longer match those values. See Procurement Overview for more information on top-down/bottom-up calculations and Re-Sync.
Related Topics |
Legal Notices
Copyright © 2015,
Oracle and/or its affiliates. All rights reserved.
Last Published Wednesday, June 17, 2015