You can define specialized phase names for drawings such as IFC - Issued for Construction, IFB - Issued For Bid. Once you define drawing phase (status) codes, you can use them in any project in the same project group.
To define a phase:
Right-click on the top-level (All Projects) folder and choose Dictionaries, Drawings, Drawing Phases. The Drawing Phases Dialog Box opens.
Click Add to open the Drawing Phases Detail Dialog Box.
In the Phase field, enter a name for the phase of up to 8 characters.
Enter a description.
From the Move Below drop-down list, select the location below which you want to insert the definition.
When you finish entering the drawing phase, click Save and Close.
Note: Phases defined here appear in all projects in the project database.