Edit Sub Item Dialog Box


Use this dialog box to edit details about an existing sub-item.

Spec Section

Select the specification section to which the sub-item applies.

Title

Enter a title for the sub-item.

Sub Item Cost:

Quantity

The number of items required.

U of M

The unit of measurement, if applicable.

Unit Price

The price per unit for the item.

Total Cost

The total cost of the sub-item appears in this field.

Comments

Any additional details about the item.

How to access this dialog box:

  1. Expand the Contract Information folder in the Project View and click Procurement.
  2. From the Procurement Items Log Window, choose a procurement item document.
  3. From the Procurement Item Document Window, click the Bid Tabulation tab.
  4. Click edit sub item next to the sub item you want to edit.