Copy From Contract Dialog Box


Use this dialog box to copy the line items from the linked contract to this proposal/change order. Select the options next to the line items you want to copy, then click Finish.

Note: For this option to appear in a change order, the change order must have originated in Change Management.

Select

Select the option to copy this line item.

Type

The line items' type.

Line Item No.

The line items' number.

Description

A brief description of the item or service.

Material

The material linked to the line item.

How to access this dialog box:

  1. Expand the Contract Information folder in the Project View and click Change Orders or Proposals.
  2. From the log window, click Edit next to a change order.
  3. From the document window, click the Line Items tab.
  4. Click Copy from Contract. You can only collect changes into a change order created directly in the Change Orders Log Window. If the change order was created in Change Management, Collect from Changes will not be visible.