Set Retainage Preferences for a Contract or Purchase Order

Previous TopicNext TopicContents

  1. In the Project View, expand a project, expand the Contract Information folder and click Purchase Orders or one of the Contracts modules.
  2. Open in Edit mode the contract or purchase order for which you want to set retainage preferences.
  3. From the Select an action drop-down list, choose Cost Options to open the Cost Options Dialog Box.
  4. In the Retainage Calculation section, select one of the following as the default method for recording retainage:
  5. Click Save. These settings control how retainage is entered in requisitions generated from this contract or purchase order.