Use this page to link to a P6 EPPM module schedule and enter initial project values and schedule dates.
Contract Date
Enter the date the contract was signed and/or approved.
Proceed Date
Enter the date work on the project is to begin.
Completion Date
Enter the date by which the project will be finished.
Schedule
Select whether you are linking this project to a P6 EPPM schedule.
Notes:
Database
Select the P6 EPPM database to connect to.
Project
Select the P6 EPPM project to link with.
Use Responsibility To Filter Activity Retrieval In Daily Reports
Mark to include P6 EPPM activities with early start and/or early finish dates that include the day of the Daily Report, and that are assigned the same Responsibility value as the Contractor field in the Daily Report Document Window.
How to access this dialog box:
Note: You will need to enter a project name and title before clicking this tab.
Legal Notices