Update Submittals Schedule Log Dialog Box


This dialog box displays information about submittals that were not updated during the schedule update from P6 EPPM. Click Print to print the log.

Project Name

The name of the project.

Project Title

The full name of the project.

Submittal No.

The number of the submittal.

Reason

The reason the submittal was not updated.

You can use this information to fix the problem.

How to access this dialog box:

  1. Click Update from Schedule in the Update Submittals Schedule object in the Workspace.
  2. Click View Log on the confirmation window.