Add Project Dialog Box – Schedule Page


Use the Schedule page of the Add Project Dialog Box to link to a P6 EPPM schedule and enter initial project values and schedule dates.

Contract Date

Click the calendar , and choose the date on which the contract was signed or approved.

Proceed Date

Click the calendar , and choose the date on which the project work is to begin.

Completion Date

Click the calendar , and choose the date by which the project will be finished.

Schedule

Select whether you are linking this project to a P6 EPPM schedule.

Notes:

Database

Select the P6 EPPM database to connect to.

Project

Select the P6 EPPM project to link with.

Use Responsibility To Filter Activity Retrieval In Daily Reports

Mark to include P6 EPPM activities with early start and/or early finish dates that include the day of the Daily Report, and that are assigned the same Responsibility value as the Contractor field in the Daily Report Document Window.

How to access this dialog box:

  1. From the Project View, right-click on the top-level folder (All Projects) and select New Project.
  2. In the Add Project Dialog Box, click the Schedule tab.

    Note: You will need to enter a Project Name and Title before clicking this tab.



Legal Notices
Copyright © 2015, Oracle and/or its affiliates. All rights reserved.