The Cost Worksheet provides a central location for tracking all project costs. You can compare budgeted and committed costs to actual costs for each work element. Open the Cost Worksheet Log Window from the Contract Information folder. Costs are organized by cost codes, which represent various categories of project work. Using Project Settings Dialog Box, you can set which cost documents are distributed.
Once you've recorded the payment in the Invoice Dialog Box, you can distribute it to the Actuals side of the Cost Worksheet by opening an invoice and using the Costing section.
Costing out your invoices is optional. You do not have to use the Cost Worksheet to use invoices or requisitions. Also, you can only cost out your invoices if you costed out the associated contract or purchase order.
If you know you'll be using the Cost Worksheet, there are three ways to add cost codes:
If you do not distribute the entire amount of the invoice, Contract Management applies the non-distributed amount to a cost code called Not Costed. Using Project Settings, you can set Contract Management so that the entire amount of the invoice is distributed to defined cost codes.
Related Topics |
Legal Notices
Copyright © 2015,
Oracle and/or its affiliates. All rights reserved.
Last Published Wednesday, June 17, 2015